Monorail
Project information
- Location: NCC Monorail
- Contractor: Orascom
- Consultant: ECG
- Client: National Authority for Tunnels, Ministry of Transportation
- Area: 1.Cairo stadium. - 2.Hesham Barakat. - 3.Noury Khattab - Al-Azhar - 4.Seventh District
- System: Sherif Ali Hassan
Monorail
Challenge 1: One of the significant challenges OMSI encountered was achieving reliable aluminum fixation on steel, a process that required addressing both technical and material compatibility issues.
Challenge 2: Installing a façade over large areas presented challenges due to the uneven thickness of the wall plaster, requiring careful adjustments to ensure proper alignment and stability.
Challenge 3: Establishing connections between curved profiles and segmented glass solutions posed challenges both during the preparation of shop drawings and throughout the installation process.
Challenge 4: OMSI’s work on station projects was located in densely populated and crowded areas, where the use of cranes for installation was sometimes restricted or prohibited. Stations in OMSI scope are the only one that include escalators